City of Lincoln  
City of Lincoln/
Lancaster County
Purchasing

Special Provisions For Construction Contracts for City of Lincoln/Lancaster County Public Building Commission

 


                
1.Contract Documents
1.1 Copies of the plans, specification documents and contract documents may be obtained at the office of the Purchasing Agent. 1.2 Bidders are required to examine the same, and satisfy themselves that all requirements are fully understood.
2. Project Manager
2.1 The definition of "Project Manager" as used in this Specification Document shall mean the Building Commission Officer or by or through that person's duly authorized assistant:
3. Site Visitation
3.1 Bidders shall inform themselves of the conditions under which the work is to be performed, concerning the site of work, the structures, obstacles which may be encountered and all other relevant matters concerning the work to be performed. 3.2 The contractor will not be allowed any extra compensation by reason of any matter or thing concerning which he might fully have informed himself prior to bidding. 3.3 A site inspection may be arranged by contacting
4. Escalator Clause
4.1 An escalator clause or any qualification of price conditions which makes it possible to bill at a price higher than price quoted will disqualify the bid, unless such maximum billing price or percentage of increase is definitely shown on the Proposal, in which case such higher price will be used for comparison of bids.
5. Contract, Bonds And Insurance
5.1 Within fourteen (14) calendar days after the award of bid, the successful bidder must execute a written contract between the bidder and the Building Commission, which contract will incorporate the Commission's specification documents, and be on contract forms provided by the Building Commission. 5.2 Also within such period, the successful bidder must furnish construction bonds, in a sum not less than the contract price executed by the bidder and by a corporate surety company authorized to transact business in the State of Nebraska. See sample bonds and commentary, attached. 5.3 Also, within such period, the successful bidder must furnish evidence of insurance in accordance with the attached "Insurance Clause to be Used for All Building Commission Contracts".
6. Payment To Unemployment Compensation Fund
6.1 The contractor and his subcontractors must pay to the Unemployment Compensation Fund of the State of Nebraska, unemployment contributions and interest due under the provisions of Section 48-601 through 48-669, Nebraska Reissue revised Statutes for 1943, on wages paid to individuals employed in the performance of the contract.
7. Health And Safety Regulations
7.1 The contractor and his subcontractors shall in all respects comply with the terms and provisions of Sections 48-425 through 48-435, Nebraska Reissue Revised statutes of 1943, generally pertaining but not limited to scaffolding and flooring, and shall perform fully on behalf of the Building Commission such requirements as said sections may impose upon the Building Commission. 7.2 The Contractor and his subcontractors shall likewise comply and perform with respect to any and all other applicable health and safety regulations.
8. Delays
8.1 With written permission of the Project Manager, the completion date may be extended if unsuitable weather or any force majeure should halt progress during the construction period.
9. Clean up
9.1 The Contractor shall be responsible for keeping the premises free of waste materials or rubbish resulting from his operations or the operations of his subcontractors. 9.2 The Contractor shall remove equipment, scaffolding and surplus materials from the premises when the need for keeping them on the job not longer exists.
10. Inspections
10.1 Inspections in general will be conducted by Project Manager. 10.2 The contractor shall be responsible for contacting City Building and Safety Department for inspections required by City Codes for this type of public improvement.
11. Access And Parking
11.1 The Contractor shall park all vehicles in an area as designated by the Project Manager during construction. 11.2 Access to the construction site shall be gained as directed by the Project Manager.
12. Permits, Fees And Notices
12.1 Contractors shall secure all permits, licenses and certificates of inspections and occupancy that may be required by the City of Lincoln. 12.2 Contractor will be required to pay for said permits, licenses and certificates for this project: [X] YES. [] NO.
13. Errors And Omissions
13.1 If any errors or omissions are found in the drawings or specifications or other documents during construction, the Contractor shall notify the Project Manager of such error or omission, and request clarification before proceeding with the work.
14. Temporary Utilities
14.1 The contractor shall be responsible for securing and setting up all needed temporary utilities.
15. Pre-construction Conferences
15.1 Prior to starting any work, the contractor shall meet with the Project Manager for clarification of construction procedures and work to be accomplished. 15.2 At this time the contractor shall present his planned work schedule together with estimated completion date.
16. Progress Schedule
16.1 The Contractor, immediately after being awarded the contract, shall prepare and submit for the Project Manager's approval an estimated progress schedule for the work. 16.2 The progress schedule shall be related to the entire project to the extent required by the Contract Documents. 16.3 This schedule shall indicate the dates for the starting and completion of the various states of construction and shall be revised as required by the conditions of the work, subject to the Project Manager's approval.
17. Guarantee
17.1 As a minimum requirement of the Building Commission, the contractor shall guarantee all materials and workmanship for a period of one (1) year following completion of the project.
18. Notice To Proceed
18.1 The Contractor shall not begin construction until receiving written "Notice to Proceed" from the Project Manager.
19. Purchasing Agent Appointment And Exempt Sale Certificate
19.1 The Contractor performing work for Lincoln-Lancaster County Public Building Commission will be issued a Purchasing Agent Appointment and Exempt Sale Certificate signed by the Purchasing Agent. 19.2 It is to be used by the Contractor and his Subcontractors when purchasing tangible personal property to be actually incorporated into the contract work. 19.3 It does not apply to either: 1. The purchase of materials to be used but not incorporated into the contract work, including but limited to, form lumber, scaffolding, etc., or 2. The purchase or rental of machinery, equipment or tools owned or leased by the Contractor or his subcontractors and used in performing the contract. 19.4 The contractor may reproduce copies of the original of the aforesaid document to furnish to his or his subcontractor's suppliers on each invoice or order. 19.5 The Contractor (or Subcontractor for the subcontractor's suppliers) shall enter the supplier's name and address, the date, the invoice or order number, a description of the items, and the amount in the spaces provided and shall sign the certificate on the line provided for the "Purchaser's Agent".
20. Liquidated Damages
20.1 If the Contractor fails to complete the Contract prior to the completion date, considering approved extensions of time, liquidated damages will be charged for each working day that the work remains incomplete. 20.2 Working days shall be considered any day except Saturday, Sunday, or Building Commission authorized holidays, which the contractor is not prevented by weather, soil conditions, or other conditions beyond the contractor's control, as determined by the Project Manager, from proceeding with work to complete the contracted project. 20.3 The amount of liquidated damages will be deducted from the money due the Contractor prior to final payment or in the case where the remaining amount due the Contractor is less than the total amount of liquidated damages, the Building Commission shall have the right to recover the difference from the Contractor or his Surety. 20.4 Unless specifically amended or modified by the special provisions, the schedule below shall establish the daily amount of the liquidated damages: Bid Amount: UP TO AND LIQUIDATED DAMAGES MORE THAN INCLUDING PER WORK DAY $ 0 $ 100,000 $ 100 100,000 500,000 200 500,000 1,000,000 300 1,000,000 AND UP 400 20.5 The amounts set forth in the above schedule are not to be considered punitive, but rather predetermined and reasonable amounts to compensate for the detriment to the public and to defray expenses incurred by the Building Commission due to the delay in the completion of the project.
21. Asbestos
21.1 No materials whatsoever shall be utilized in the construction, reconstruction or remodeling which may contain asbestos as defined under Nebraska Asbestos Control Act, Article 71, Section 71-6301 through 71-6317 of the Revised State of Nebraska Code. 21.2 The removal of any asbestos containing material shall be in strict compliance with the said Nebraska Asbestos Control Act and appropriate Occupation Safety and Health Administration (OSHA) Regulations including but not limited to 29CFR, 1910-1200, 1926-58 and 1910-1001 and the Environmental Protection Agency, (EPA) NESHAPS Standard for Asbestos 40CFR 61 Subpart A and M covering emission standards, 42 USCA 7401-7642 - CLEAN AIR ACT, 40 CFR Part 763 Subpart G-Asbestos Abatement Projects, 40 CFR Part 763.120 Subpart G-Worker Protection Rule and such other local, state or federal applicable rules or regulations.
22. Laws
22.1 The Laws of the State of Nebraska shall govern the rights, obligations, and remedies of the Parties under this proposal and any agreement reached as a result of this process.

Purchasing