Beginning Tuesday, Sept. 3, Cotner Blvd. from 66th to 68th streets will be closed during the day (between morning and afternoon rush hours) for gas main replacement. The project is expected to be completed by Sept. 20.

Resurfacing work on Havelock Ave. begins Wednesday, September 4, with 70th to 73rd streets closed until Sept. 20. On Monday, September 9, Havelock Ave. from Touzalin to 70th will close until Oct. 12. The intersection of 70th and Havelock will remain open during the project.

When the Huskers have home football games, these sections of Havelock will reopen from Friday afternoons until Sundays.

For more information on City construction projects, visit lincoln.ne.gov (keyword: projects).