Water Main Replacements
North 75th Street, Dotson Road and Broadview Drive

Project Information

February 28, 2014

The City of Lincoln proposes to replace the existing water main along North 75th Street and Broadview Drive beginning on March 10, 2014, weather permitting. The water main on North 75th Street will be replaced from Steinway Road to Dotson Road, and along Dotson Road from North 75th Street to Broadview Drive. The water main on Broadview Drive will be replaced from Steinway Road to Skyway Drive. Construction is expected to take twelve weeks and will begin on North 75th Street. Upon completion of the installation and chlorination of all water mains, the contractor will change over water service lines to the new water main, again beginning on North 75th Street.

K2 Construction will be the contractor. They will perform the work under a total street closure with the road open to local traffic only (see street closure map, below). During construction, access to driveways may be restricted at times. The City and the contractor will work with residences regarding their access during construction.

Project Contacts

  • Construction Project Manager

    Zach Becker
    City of Lincoln, Engineering Services
    Phone: 402-613-3763
    Email: zbecker@lincoln.ne.gov

  • Project Contractor

    Charlie Heng
    K2 Construction
    Phone: 402-416-6748
    Email: cheng@k2construction.biz