Project Information
Detour Map
14th Street is scheduled to be closed from Fletcher to Humphrey March 5–June 29, 2012.
This project consists of improving 14th Street from the Fletcher Avenue to Alvo Road. Planned improvements for the new street include the following:
- 14th Street will be widened to two lanes in each direction with a center median between the Interstate 80 bridge and Alvo Road.
- Left- and right-turn lanes will be built at the intersections of 14th Street with Julesburg Drive, Humphrey Avenue and Fletcher Avenue.
- A two-lane roundabout will be built at the intersection of 14th and Alvo.
- A bike trail will be built on the west side of 14th from the I-80 bridge to Humphrey, and sidewalks will be built on the remaining portions of the project.
Work is scheduled to begin in mid to late February and will require road closures on 14th Street throughout construction. The construction will be completed in several phases. The first phase includes building drainage structures south of Humphrey along with the 14th St. and Humphrey Intersection. This intersection will be phased to allow traffic to be maintained on Humphrey Avenue. The second Phase will include roadway work from Fletcher Avenue to Humphrey. Access to the acreages on the west side of 14th will be maintained throughout the construction of this phase. Phase 3 will move to the north side of the project between Julesburg Dr. and Alvo Road. This work will not begin until after the 2012 school year and will be complete before school begins again in the fall. The last phase will connect the completed pieces of roadway between Humphrey and Julesburg and is not scheduled to be complete until late fall 2012. The roadway is scheduled to be open to traffic from Fletcher to Alvo Road by November 21, 2012, with a final completion date for the project of May 30, 2013.
Construction Phasing
- Phase I -
- North 14th Street/Humphrey Avenue Intersection - February 2012 to March 2012
- Phase II -
- Interstate 80 to south of Humphrey Avenue - March 2012 to June 2012
- Phase III -
- South of Julesburg Drive to North of Alvo Road - September 2012 to November 2012
- Phase IV -
- Humphrey Avenue to Julesburn Drive - September 2012 to November 2012
- NDOR I-80 Bridge -
- Mid-September 2011 to Mid-August 2012
Schedule subject to change due to weather or other delays or conflicts.
Public Participation
- Open House - Wednesday, January 25, 2012
- 5:30 to 7:30 p.m.
- Kooser Elementary School
- 7301 N. 13th St.
- Open House Handout (1.56 M)
Project Contacts
For more information, please contact:
- Devin Biesecker
City of Lincoln Design Project Manager
Engineering Services
(402) 937-5515
dbiesecker@lincoln.ne.gov - Warren Wondercheck
City of Lincoln Construction Project Manager
Engineering Services
(402) 540-2750
wwondercheck@lincoln.ne.gov