A City Council public hearing for the One and Six Year Streets and Highways Improvement Program is scheduled for:
| Date: | August 7, 2006 |
|---|---|
| Time: | 4:30 p.m. |
| Place: | City Council Chamber, 555 South 10th St., Lincoln, NE. |
This public hearing is held to fulfill State statutory requirements and also serves as the public hearing for the City's Capital Improvements Program.
All interested individuals are invited to attend this public hearing. Individuals unable to attend can submit their written comments to Roger Figard, City Engineer, Engineering Services, 531 Westgate Boulevard / Suite 100, Lincoln, NE 68528, by August 17th, 2006.
City of Lincoln, Nebraska Public Works & Utilities Department---Phone: 441-7711
The One Year Program for Fiscal Year 2007
- Projects Proposed for Final Design, Right-of-way Acquisition, Construction or Engineering Study.
These projects include:
- (12) Antelope Valley Phase 1 Project - Big "T"
- (13) Antelope Valley Phase 2 Project - Channel Wall
- (14) Antelope Valley Phase 3 Project - Channel Wall
- (15) Antelope Valley Phase 1 Project - Planning/Coordination
- (16) Antelope Valley Phase 1 Project - Planning/Design
- (17) Antelope Valley Phase 1 Project - 'P' and 'Q' Street Bridges.
- (18) Antelope Valley Phase 1 Project - 'N' Street Bridge.
- (19) Antelope Valley Phase 1 Project - 'O' Street Bridge and Road.
- (20) Antelope Valley Phase 1 Project - "East Leg" of the Big "X"
- (21) Antelope Valley Phase 1 Project - 'J' Street Bridge.
- (22) Antelope Valley Phase 1 Project - South Street Bridge.
- (23) Antelope Valley Phase 1 Project - North/south Road, 'K' Street to North of 'Q' Street.
- (24) Antelope Valley Phase 1 Project - North/south Road, North of 'Q' Street to 'Y' Street.
- (25) East 'O' Street from 42nd to 52nd Streets
- (26) Harris Overpass Replacement
- (27) South Beltway
- (28) East Beltway
- (29) SW 40th Viaduct
- (30) Adams and NW 12th Street Bridge Repair
- (31) 48th Street and Huntington Avenue
The One Year Program Also Includes Projects Which Continue Thru the Entire Six Year Program:
- 'Intelligent Transportation Infrastructure Improvements, Traffic Optimization, and Management';
- 'Miscellaneous, Emergency and Safety Projects and Operational Improvements';
- 'Modify, Replace, or Install Traffic Signal Equipment and Communication Links';
- 'Studies, Preliminary Engineering and Right-Of-Way Acquisition';
- 'Upgrade Built Environment and Traffic Calming';
- 'City Subsidy for Repaving, Paving Districts and Federal Aid Projects;'
- 'Landscaping in Connection with Street Improvement Projects';
- 'Misc. Engineering, Construction and Computer Records';
- 'Sidewalk Maintenance and Repair';
- 'Arterial/residential Rehabilitation and Intersection Projects'.
Second Through Sixth Year Program (Fiscal Years 2008-2012)
- Projects That are in Some Phase of Development or Will Enter the Street Planning Process.
These projects include:
- (13) Antelope Valley Phase 2 Project - Channel Wall
- (14) Antelope Valley Phase 3 Project - Channel Wall
- (15) Antelope Valley Phase 1 Project - Planning/Coordination
- (17) Antelope Valley Phase 1 Project - 'P' and 'Q' Street Bridges.
- (18) Antelope Valley Phase 1 Project - 'N' Street Bridge.
- (19) Antelope Valley Phase 1 Project - 'O' Street Bridge and Road.
- (20) Antelope Valley Phase 1 Project - "East Leg" of the Big "X"
- (21) Antelope Valley Phase 1 Project - 'J' Street Bridge.
- (22) Antelope Valley Phase 1 Project - South Street Bridge.
- (23) Antelope Valley Phase 1 Project - North/south Road, 'K' Street to North of 'Q' Street.
- (24) Antelope Valley Phase 1 Project - North/south Road, North of 'Q' Street to 'Y' Street.
- (26) Harris Overpass Replacement
- (27) South Beltway Project
- (28) East Beltway
- (29) SW 40th Viaduct Project
- (32) 48th Street and Madison Avenue