56th from Highway 2 to Spruce

October 10, 2013

The City of Lincoln proposes to mill and overlay South 56th Street from Nebraska Highway 2 to Spruce Street beginning the week of October 21, 2013, weather permitting. The existing asphalt pavement will be milled off and overlaid with new asphalt and pavement markings. Pedestrian curb ramps at Shady Creek Road, Edgewood Drive, La Salle Street, and Spruce Street will be reconstructed to meet ADA standards.

Pavers Inc. will be the contractor. They propose to perform the work under lane closures. Access to side streets and driveways will be limited for short durations during the milling and asphalt operations. Pavers and the City will work with businesses and residents regarding access during construction.