North 31st Street Lift Station – Pump Installation,
Electrical and HVAC Improvements
Lincoln Wastewater System (LWWS) proposes to upgrade the existing North 31st Street Lift Station. The primary focus of the Pump Installation, Electrical and HVAC Improvements project is to replace two existing 25 hp pumps with two 60 hp pumps to accommodate anticipated future flows to the lift station. Associated improvements will also be made to the electrical system including motor control replacement for the pumps. Improvements to the HVAC system will include modifications to provide for air exchange per current codes.
Project Summary:
- Project Information:
- Replacement of two existing 25 hp pumps with two 60 hp pumps. Motor Control replacement, HVAC rehabilitation and associated electrical improvements.
- Project Construction Cost as Bid:
- $244,500.00
Project Schedule
- Bids Received
- May 17, 2006
- Executive Order Signed
- August 7, 2006
- Notice to Proceed
- August 10, 2006
- Substantial Completion
- 180 Calendar Days (February 27, 2007)
- Final Completion
- 210 Calendar Days (March 29, 2007)
Contact Information
- Lincoln Wastewater System
- Steve Crisler (402) 441-7966
- City Project No. 502008
- Specification No. 06-143
- HDR Engineering
- Kent Prior (402) 742-2906
- HDR Project No. 12595
- Judds Brothers Construction Company
- Kevin Steele (402) 467-4666