Upper Southeast Salt Creek Sub-Basin Sewers

Phase I


City of Lincoln Logo HDR Logo

Upper Southeast Salt Creek Sub-Basin Sewers – Phase I

Phase 1 commences with a connection to the Upper SE Salt Creek Trunk Sewer and extends east and northeast along the existing drainage channels to a location east of 27th Street and north of Rokeby Road and has been completed.

The project included 5244 LF of 24 to 30 inch diameter sewer pipe. Testing of the sewer line was done by Lincoln Wastewater System, Dobson Brothers Construction and HDR Engineering Inc. and was completed in August of 2006.

Bids were received on November 9, 2005, from 10 contractors. Dobson Brothers Construction was the successful low bidder for the project with a bid of $693,247.43. Dobson completed installation and testing of the sanitary sewer in August 2006 and has restored the project area. Dobson's total construction cost was $674,922.29.

Project Summary as of January 15, 2007

Project Information:
Phase 1 - 3,209 LF 30" Sewer, 1,191 LF 27" Sewer, 844 LF 24" Sewer, Bored Crossing of South 27th Street, Open-Cut Crossing of Rokeby Road
Construction Cost (with Change Orders):
$674,922.29

Project Schedule

Bids Received
November 9, 2005
Executive Order Signed
December 14, 2005
Notice to Proceed
January 17, 2006
Final Completion
August 15, 2006

Contact Information

Lincoln Wastewater System:
Brian Kramer (402) 441-7987
City Project No. 502 458
Specification No. 04-313
HDR:
Terry McArthur (402) 742-2905
HDR Project No. 21257
Dobson Brothers Construction:
Darrin Duffy (402) 474-5115