Upper Southeast Salt Creek Sub-Basin Sewers - Phase III
Phase 3 commences with a connection to the Upper SE Salt Creek Sub-Basin Sewer-Phase 1 at approximately South 36th Street north of Rokeby Road and extends east along the existing drainage channel east of South 40th Street.
Coordination meetings have been held with the City of Lincoln Planning Department, Lincoln Water System, Watershed Management, Lower Platte South Natural Resources District, Engineering Services, Parks and Recreation Department, and private utilities in the project area. A public meeting was held on April 12, 2005 at the Walt Branch Library to present the project.
Bids were received on July 26, 2006 from six (6) contractors. General Excavating was the successful low bidder for the project with a bid of $333,785. The project is currently under construction.
Project Summary as of January 15, 2007
- Project Information:
- Phase 3 - 2,609 LF 21" Sewer, Bored Crossing of South 40th Street
- Project Construction Cost as Bid:
- $333,785.00
Project Schedule
- Phase 3 Bids Received
- July 26, 2006
- Executive Order Signed
- September 8, 2006
- Notice to Proceed
- September 18, 2006
- Construction Commenced
- November 29, 2006
- Phase 3 Substantial Completion
- 150 calendar days (Feb. 14, 2007)
- Phase 3 Final Completion
- 180 calendar days (Mar. 16, 2007)
Contact Information
- Lincoln Wastewater System:
- Brian Kramer (402) 441-7987
- City Project No. 502 459
- Specification No. 06-211
- HDR:
- Terry McArthur (402) 742-2905
- HDR Project No. 21257
- General Excavating:
- Jim Brunner (402) 467-1627
View Project Location Map (378 K) 