Upper Southeast Salt Creek Sub-Basin Sewers - Phase III

Phase 3 commences with a connection to the Upper SE Salt Creek Sub-Basin Sewer-Phase 1 at approximately South 36th Street north of Rokeby Road and extends east along the existing drainage channel east of South 40th Street.

Coordination meetings have been held with the City of Lincoln Planning Department, Lincoln Water System, Watershed Management, Lower Platte South Natural Resources District, Engineering Services, Parks and Recreation Department, and private utilities in the project area. A public meeting was held on April 12, 2005 at the Walt Branch Library to present the project.

Bids were received on July 26, 2006 from six (6) contractors. General Excavating was the successful low bidder for the project with a bid of $333,785. The project is currently under construction.

Project Summary as of January 15, 2007

Project Information:
Phase 3 - 2,609 LF 21" Sewer, Bored Crossing of South 40th Street
Project Construction Cost as Bid:
$333,785.00

Project Schedule

Phase 3 Bids Received
July 26, 2006
Executive Order Signed
September 8, 2006
Notice to Proceed
September 18, 2006
Construction Commenced
November 29, 2006
Phase 3 Substantial Completion
150 calendar days (Feb. 14, 2007)
Phase 3 Final Completion
180 calendar days (Mar. 16, 2007)

Contact Information

Lincoln Wastewater System:
Brian Kramer (402) 441-7987
City Project No. 502 459
Specification No. 06-211
HDR:
Terry McArthur (402) 742-2905
HDR Project No. 21257
General Excavating:
Jim Brunner (402) 467-1627