West 'O' Street Trunk Sewer Extension - Phase I
Project Description
The Phase 1 commences with a connection to the West 'O' Street Trunk Sewer at SW 40th Street, north of the BBNSFR right-of-way. The sewer will service an area bounded by West Holdrege Street, the BNSFR right-of-way, West 48th Street, and West 56th Street.
The project includes a 540 LF section of 36 inch 'Flowtite' fiberglass pipe for testing and evaluation by the City.
Bids were received on February 23, 2005, from 7 contractors. HR Bookstrom Construction was the successful low bidder for the project with a bid of $1,439,600.
Project Summary
- Project Information:
- Phase 1 - 1,279 LF 36" Sewer, 540 LF 36" Sewer (Flowtite), 1,131 LF 18" Sewer, 4,336 LF 15" Sewer, Open-Cut Crossing of South 40th Street, Bored Crossing of West 'O' Street, Bored Crossing of Interstate-80
- Construction Cost (including Change Orders):
- $1,394,321.50
Project Schedule
- Bids Received
- February 23, 2005
- Executive Order (73086) Signed
- April 1, 2005
- Notice to Proceed
- May 10, 2005
- Substantial Completion
- April 26, 2006
- Final Completion
- June 15, 2006
Contact Information
- Lincoln Wastewater System:
- Brian Kramer (402) 441-7987
- City Project No. 701019
- Specification No. 05-032
- HDR (Consulting Engineer):
- Kent Prior (402) 742-2906
- HDR Project No. 12733
- HR Bookstrom Construction:
- Derek Bookstrom (402) 464-4342