Project Description
Phase 3 commences with a connection to the West 'O' Street Trunk Sewer-Phase 1 at approximately SW 42nd Street, north of the BNSFR right-of-way. The sewer will service an area bounded by West Holdrege Street, the BNSFR right-of-way, West 40th Street, and West 48th Street.
Bids were received on October 11, 2006 from six contractors. H. R. Bookstrom was the successful low bidder for the project with a bid of $392,385.00. H. R. Bookstrom has commenced construction and continues to work to achieve completion of the project.
Project Summary as of January, 2007
- Project Information:
- Phase 3 - 3,180 LF 15" Sewer, Bored Crossing of West 'O' Street, Bored Crossing of Interstate 80.
- Opinion of Probable Construction Cost:
- $392,385.00
Project Schedule
- Bid Received
- October 11, 2006
- Executive Order (77735) signed
- November 13, 2006
- Notice to Proceed
- December 1, 2006
- Substantial Completion
- April 29, 2007
- Final Completion
- May 29, 2007
Contact Information
- Lincoln Wastewater System
- Brian Kramer (402) 441-7987
- City Project No.701059
- HDR Engineering
- Kent Prior (402) 742-2906
- HDR Project No. 12733
View Project Location Map (359 K) 