Construction Update – March 2008
Phase 1 - Northeast Salt Creek Basin Sanitary Trunk Sewer Improvements
Project No. 701479

Construction of the Northeast Salt Creek Basin Sanitary Trunk Sewer project began on October 15, 2007. The new trunk line begins on N. 70th St. at a connection to the existing Deadman's Trunk Sewer and then proceeds north and west along Salt Creek to N. 56th St. The trunk sewer will be tunneled under N. 56th St. so traffic flow will not be interrupted on the street. This line will provide service to future growth areas generally located north of Salt Creek and west of N. 70th St in the basin.

Advance funding for construction is being provided by a developer and development in the basin. Tax increment financing (TIF funds) and sanitary sewer revenue funds are to be used for reimbursing the developer for the advance funding.

Current construction work includes building siphon structures, installing valve gates, video television inspection, testing of manholes and piping, and restoring of top soil.

Click for larger view
Installation of 36 inch diameter Trunk Sewer

Click for larger view
Backfilling of Sanitary Sewer Manhole

Project Summary

General:
     Trunk Sewer Pipe36 inch diameter - 7,024 LF
48 inch diameter - 60 LF
     Inverted Siphon Pipe:1 - 12 inch diameter - 357 LF
1 - 16 inch diameter - 357 LF
1 - 27 inch diameter - 357 LF
Total Project Cost:$ 2,500,000 (Estimated)
Project Construction Cost:$1,927,700
Construction Status:95% (as of March 7, 2008)
Funding:Tax Increment Financing (TIF) & Sanitary Sewer Revenue Funds

Project Schedule

Start of ConstructionOctober 15, 2007
Substantial CompletionJune, 2008
Final CompletionSeptember, 2008

Project Contacts

T. J. Osborn Construction, Inc. (Construction Contractor):

  • Keith Schriner - Superintendent
  • (402) 432-4281

HDR Engineering Inc.

  • Kent Prior – Project Manager
  • Kent.Prior@hdrinc.com
  • (402) 742-2906
  • Russell Freye - Construction Observer
  • (402) 943-9119