Oak Creek Basin Trunk Sewer - Phase 1

The Oak Creek Trunk Sewer Study provides an analysis of existing sewer capacities based upon alternate alignment configurations, alternate flow contributions to existing and proposed new sewers, and for alternate pipe design conditions. The Oak Creek Trunk Sewer Study also provides an opinion of costs for alternative pipe sizing configuration, flow conditions, and pipe conditions. Lincoln Wastewater System and HDR Engineering initiated Final Design of the Oak Creek Basin Trunk Sewer - Phase 1 project in July 2006. The Phase 1 improvements propose to replace sanitary sewer along NW 41st Street from Air Park Road to West Mathis Street and will also include a new barrel and manhole improvements for the existing Oak Creek siphon at West Mathis Street.

Project Summary:

Project Information:
Replacement of sewer from Air Park Road to West Mathis Street. Proposed new barrel and manhole improvements for the existing Oak Creek siphon at West Mathis Street.
Opinion of Probable Project Cost:
$1,682,000

Project Schedule

Final Design Documents
January 2007
Proposed Bid Date
March 2007
Construction
April 2007 - November 2007

Project Contacts

Lincoln Wastewater System
Gary Thalken (402) 441-7967
City Project No. 502941
HDR Engineering
Kent Prior (402) 742-2906
HDR Project No. 20843