Construction Update – November, 2007
Oak Creek Basin Sanitary Trunk Sewer Improvements – Phase 1
Project No. 502941
Construction of Phase I of the Oak Creek Basin Sanitary Trunk Sewer Improvements project began on Oct. 1, 2007. Phase 1 is the initial phase of a long term multi-phased project to replace sections of the existing trunk sewer system in this basin that are undersized with new larger lines. The new larger lines will provide additional conveyance capacity for future growth in the Oak Creek Basin. The project is located in the Lincoln Airport Authority Airpark industrial area.
This project includes: replacing an existing under capacity sanitary trunk sewer along NW 41st Street from Air Park Road to West Mathis Street with a new 42 inch diameter trunk sewer; and, replacing of an existing under capacity siphon crossing Oak Creek at Air Park Road.
Work has started on realigning an existing storm sewer near NW 41st Street that is in conflict with the new trunk sewer grade and replacement of the siphon and related structures. Two (2) new 12 inch diameter HDPE pipes are being installed using directional drilling technology to avoid disruption to Oak Creek.
Project Summary
- Total Project Cost:
- $1, 255,000 (Estimated)
- Project Construction Cost:
- $900,700
- Construction Status:
- 5% as of November 1, 2007
- Funding:
- Sanitary Sewer Revenue Funds
Project Schedule
- Start of Construction
- October 1, 2007
- Substantial Completion
- April, 2008
- Final Completion
- May, 2008
Project Contacts
General Excavating (Construction Contractor):
- Brian Egr – Project Manager
- begr@generalexcavating.com
- (402) 416-6832
HDR Engineering Inc.
- Kent Prior – Project Manager
- Kent.Prior@hdrinc.com
- (402) 742-2906
- Bob Oliver & Brent Peterson (Construction Observers)
- (402) 802-7433
Lincoln Wastewater System:
- Brian Kramer – Project Manager
- Supt. of Wastewater Collection
- bakramer@lincoln.ne.gov
- (402) 441-7987