Wastewater Projects: Theresa Street Wastewater Treatment Facility

Construction Update - September 2006


City of Lincoln Logo HDR Logo

Theresa Street Wastewater Treatment Facility - Nitrification and Capacity Improvements Construction Project Update - September 2006
Project No. 502420

Click for larger view
Aerial View of Theresa St. Construction Progress (looking southeast)
Acrobat (PDF) Version (139 K) Acrobat Document

Construction of advanced treatment process and capacity improvements to the Lincoln Wastewater System's Theresa St. Wastewater Treatment Facility to remove ammonia and increase capacity to meet new National Pollutant Discharge Elimination System (NPDES) permit limits is underway. The improvements provide additional capacity for meeting future growth requirements and the City's continuing obligations to protect the public health and the environment. When improvements are complete the total treatment capacity will be 27.4 million gallons per day.

The largest portion of the improvements is construction of a new central treatment train process that utilizes an advanced form of the current Activated Sludge (AS) treatment process. The construction project also includes modifications and improvements to the existing east and west side treatment trains to provide for nitrification treatment of the wastewaters. For a more detailed description of the improvements view the previous fact sheet (168 K) Acrobat Document.

Click for larger view
New Central Train - Aeration Basin and fine bubble air diffusion equipment

Click for larger view
New Central Train - Final Clarifier Basin and clarifier mechanism

A unique phased construction plan and schedule, developed by the design engineer and city treatment facilities staff during the design, allows for the new central train facilities and existing treatment improvements to be constructed, while maintaining treatment of daily wastewater flows by using the remaining existing treatment process trains and facilities.

Project Summary: as of September 2006

Total Project Cost:
$24,830,000 (Estimated)
Project Construction Cost:
$18,349,395.00
Construction Status:
71% Complete (as of 8/31/06)
Funding:
Sanitary Sewer Revenue Funds

Project Schedule

Start of Construction
August 18, 2004
Substantial Completion
August 2007
Final Completion
September 2007

Project Contacts

Hawkins Construction (Construction Contractor):

HDR Engineering Inc.

  • Ron Sova - Project Manager
  • ron.sova@hdrinc.com
  • (402) 399-1335
  • Rob Mayer - Construction Observer
  • (402) 639-2965

Lincoln Wastewater System:

Background Information

Acrobat (PDF) Version of Project Update (185 K) Acrobat Document