2005 Stormwater Bond Issue

22nd and 'X'


22nd & 'X' Area Improvements

Contact Person:
Holly Lionberger
402-326-0593
Type of Project:
Construction
Urban Storm Drain Project
Description:
Approximately seven blocks of new storm drainage pipe project along the 'X' Street corridor from 26th to Antelope Creek to alleviate localized flooding impacts.
Project Status:
Construction Complete
Consultant:
EA
Contractor:
Pavers, Inc.
Photos:
Prior to Construction:

February 21 2006
'X' Street and 23rd, looking west
Flooding Prior to Construction:

May 7, 2007
UNL Maintenance facility, flooded loading bay

May 7, 2007
Removing sediment from loading bay

May 7, 2007
Flooding of existing location

May 7, 2007
Existing 15 inch pipe
Construction:

April 29, 2008
New curb inlet on N. 23rd St.

April 29, 2008
New stormdrain pipe being installed near N 24th St.

April 29, 2008
Improved drainage inlets near UNL Maintenance Facility
Map of Project: