Colonial Hills Park Water Quality & Stream Stability
- Contact Person:
- Ben Higgins
- 402-441-7589
- Type of Project:
- Design and Construction
- Best Management Practice
- Description:
- The goal of this project is to reduce the erosion problems, improve water quality and direct overflow away from the playground area in Colonial Hills Park. This will be done by stabilizing the channel banks, constructing small grade control structures and creating a water quality cell near the north end of the park.
- Note: There is no placement of an icon for this project on the accompanying map.
- Project Status:
- Construction Complete
- Consultant:
- The Flatwater Group
- Contractor:
- Gana Trucking and Excavating
- Photos:
- Prior to Construction:

March 2005
Colonial Hills Park eroding stream banks
January 2005
Colonial Hills Park streambank eroding under concrete liner
- Construction:

April 2007
April 2007- Project Fact Sheet (118 K)

- Rain to Recreation