Public Parking Lot Rehabilitation


Public Parking Lot Rehabilitation with Water Quality BMPs

Parks and Recreation Dept.
Contact Person:
Ben Higgins
441-7589
Type of Project:
Design and Construction
Best Management Practice
Description:
In an effort to proactively address the degradation of the public waters due to excessive volumes of runoff and the pollutants they contain, the City of Lincoln will be retrofitting two publicly owned paved parking lots with innovative stormwater collection and treatment systems.
Note: There is no placement of an icon for this project on the accompanying map.
Project Status:
Construction
Consultant:
EA Engineering
Construction Start Date:
Spring 2007
Estimated Construction Completion Date:
Summer 2007
Contractor:
Stephens and Smith Construction Co.
Photos:
27th and 'F':

Crushed rock subsurface storage

New porous pavement

Will have plants added in the fall
27th and Randolph:

Vegetated swale sub surface drain system

Vegetated swale before plants placed
Project Fact Sheet