27th Street Adaptive Signal Project

North 27th Street from “O” Street to I-80

Adaptive Signal Control Technologies Project

December 2020

U.S. Department of Transportation - Federal Highway Administration

The purpose of the proposed project is to improve the efficiency of traffic operations along the North 27th Street corridor. The project is needed to reduce congestion and delays. The corridor experiences a high volume of traffic and unique peaks in traffic due to a variety of factors, such as commercial and retail development, Lincoln North Star High School, and University of Nebraska event traffic.

The proposed North 27th Street, “O” Street to I-80 project would involve upgrading existing traffic signals and communication infrastructure along and adjacent to North 27th Street in the City of Lincoln, Nebraska in Lancaster County. The project, which extends from “O” Street to the westbound Interstate 80 ramp terminals, would procure and install Adaptive Signal Control Technology (ASCT) at signalized intersections within the project limits. In addition, several traffic signals in close proximity to the project will be upgraded: 25th Street & “O” Street, 29th Street & Cornhusker Highway, and Industrial Avenue & Superior Street.

  • Project Area

Scope of Work

Existing traffic signal and communication infrastructure throughout the project area would be updated or replaced, including traffic signal equipment and hardware, traffic signal cabinets, and vehicle detection systems. New communication conduit and cable would be installed where gaps in the existing fiber optic network are located. Removal and replacement of pavement panels in streets and sidewalks may be necessary to install underground components.

Project Schedule

The proposed project is currently in the preliminary design phase. The project is tentatively scheduled for construction beginning in late 2021 or early 2022. The project is tentatively expected to take 6 months.

Right-of-way

This project would be constructed within existing public property, primarily within existing City or State right-of-way (ROW) or permanent easements. Therefore, the acquisition of additional property rights from private property, such as new right-of-way (ROW), control of access (CA), permanent easements (PE), or temporary easements (TE), would not be necessary. However, a portion of the existing traffic signal equipment on the southwest corner of North 27th Street and Fair Street (northeast corner of Pentzer Park) is currently located within designated park property. Therefore, the City is proposing to declare a portion of the northeast corner of the park for transportation uses.

More Information on Pentzer Park

Potential Impacts

The project is anticipated to disturb portions of the grass in the street right-of-way (ROW) along the corridor. The existing traffic signal cabinets at the southwest corner of N. 27th and Fair Streets were found to be partially located on existing Pentzer Park property. Therefore, a narrow strip of park property would be declared for transportation use. In addition, the project would have temporary sidewalk closures and lane closures but alternate pedestrian access would be provided and the project will restore the land being used to pre-existing conditions. The back side of this fact sheet describes in more detail anticipated impacts to Pentzer Park and the MoPac Trail access.

Accommodation of Traffic

This project would be constructed under traffic with lane closures controlled by appropriate traffic control devices. Access to adjacent properties would be maintained during construction, but may be limited at times due to construction phasing requirements. Temporary lane closures for multiple days may be needed to accommodate construction equipment; however, full roadway closures and/or detours are not anticipated. Details would be determined during final design.

Estimated Construction Cost

The project construction is estimated to cost $2.6 million. The project would be funded with 90% Federal Transportation funds and 10% local funds provided by the City of Lincoln.

Public Involvement

Project Contacts

Please contact the City of Lincoln with any questions or concerns you would like to share regarding the project.

  • Doug Holle, Schemmer

    Phone: 402-488-2500
    Email: dholle@schemmer.com
    134 S. 13th Street, Suite 1100
    Lincoln, NE 68508

  • Dan Carpenter, City of Lincoln

    Email: dcarpenter@lincoln.ne.gov
    Phone: 402-441-7711
    949 W. Bond Street, Suite 200
    Lincoln, Nebraska 68521