The purpose of this project is to preserve the transportation asset, improve the reliability of Lincoln’s transportation system, and ensure the mobility of the traveling public.

Scope of Work

This project will rehabilitate the pavement along Arbor Road from 56th Street to 70th Street to improve roadway conditions as necessitated by the current pavement age and condition. The project does include the intersections of 56th Street or 70th Street.

Location Type of Work Anticipated Traffic Impact
56th St. to 210 feet east of 56th St.
  • Full Depth Concrete Replacement
  • Full closure
  • Local access to businesses would be maintained at all times
210 feet east of 56th St. to 70th St.
  • Patching with asphalt milling and overlay
  • Full closure
  • Local access to businesses would be maintained at all times

Access During Construction

Arbor Road will be closed to through traffic during construction. The project will be completed in segments, starting at 56th Street and progressing to 70th Street. Access to area businesses will be maintained at all times. Properties with multiple entrances will have one entrance open at all times unless otherwise agreed to with the property owner. Message signs will be used for advance notification of all closures, including those at minor intersections.

Construction Schedule

Construction is scheduled to begin June 8, 2020 and the project is anticipated to be completed by August 2020.

  • Project Area

Project Contacts

  • Gaylon Masek, Construction Project Manager

    City of Lincoln, LTU Project Delivery
    Email: gmasek@lincoln.ne.gov
    Phone: 402-416-7486

  • Jarred Horsky, Project Contractor

    Constructors, Inc.