Woodsdale Blvd. and Jackson Dr. from 27th to 31st

Storm Drainage and Street Resurfacing Project

April 2020

This project will construct a new storm drainage system on Woodsdale Blvd. and Jackson Dr. between 27th and 31st streets. The two streets will also be resurfaced.

Construction Schedule

Construction is scheduled to begin May 4, 2020 and is anticipated to be completed by November 2020. The storm drainage work will be completed first, followed by a complete mill and overlay of Woodsdale Blvd. and Jackson Dr.

Access During Construction

Woodsdale Blvd. and Jackson Dr. will be closed to through traffic during construction. Local access to individual properties will be maintained.

Throughout the project, driveway access will be maintained to the fullest extent possible, but it may be necessary to temporarily restrict access. The construction team will provide a 24-hour notice prior to restricting access. Residents with concerns or access needs should contact Manny Martinez with MTZ.

  • Project Area

Project Contacts

  • Mark Miller, Construction Project Manager

    City of Lincoln, LTU Project Delivery
    Email: mmiller@lincoln.ne.gov
    Phone: 402-416-5348

  • Tim Zach, Design Project Manager

    City of Lincoln, LTU Watershed Management
    Email: tzach@lincoln.ne.gov
    Phone: 402-441-7018

  • Manny Martinez

    MTZ Construction
    Email: manny.mtzllc@gmail.com
    Phone: 402-890-7062