2021 Citywide Asphalt Sealing Project

Updated August 6, 2021

This is a pavement preservation project intended to extend the life of the asphalt street. When the aging process is slowed early in the life cycle of the pavement, maintenance is less invasive and much less expensive. By applying a sealant to the entire roadway, we are able to stabilize and preserve the oil in the asphalt surface which will help retain the flexibility of the pavement and extend the life of the driving surface.

Locations and Schedule

The project is scheduled to begin August 4, 2021 and be completed August 12, 2021. Dry conditions are necessary for successful application, so project dates are dependent on suitable weather conditions.

Streets are tentatively scheduled to be treated on the following days:

Wednesday, August 4, 2021
  • NW 10th Street from W Harvest Drive to NW Gary Street
  • 9th Street from Judson Street to Hartley Street
  • Fairfield Street from 14th Street to 20th Street
  • 48th Street from Superior Street to the Landfill
  • Judson Street from 60th Street to 66th Street
  • 63rd Street from Judson Street to Fremont Street
  • 68th Street from Fremont Street to Morrill Avenue
Thursday, August 5, 2021
  • Spruce Street from 48th Street to 56th Street
Friday, August 6, 2021
  • Deerwood Drive from Elkcrest Drive to 67th Street
  • Seven Oaks Neighborhood
  • Briarhurst Neighborhood
Monday, August 9, 2021
  • Haymarket Downtown
    • 8th Street from “O” Street to “S” Street
    • 9th Street from “R” Street to “S” Street
    • “S” Street from 8th Street to 9th Street
  • 56th Street from Vine Street to Adams Street
Tuesday, August 10, 2021
  • Haymarket Downtown
    • “P” Street from 7th Street to 9th Street
    • “R” Street from 8th Street to 9th Street
  • 18th Street from “O” Street to “Q” Street
  • 33rd Street from Holdrege Street to Madison Avenue
Wednesday, August 11, 2021
  • Haymarket Downtown
    • “Q” Street from 7th Street to 9th Street
  • Old Cheney Road from 40th Street to NE-2
Thursday, August 12, 2021
  • Wilshire Boulevard from Santa Monica Avenue to El Avado Avenue
  • Randolph Street from 56th Street to Sunrise Road (Dead End)
  • 30th Street from Bonacum Drive to Calvert Street
  • Project Area

Access During Construction

The process requires closure of the street for two to three hours while a liquid sealant is applied. After two hours, sand is applied and the street is reopened, but motorists are urged to drive slowly. Sand will be swept up about two days later, depending on weather.

No parking will be allowed on the street while work is being completed. “No Parking” signs will be posted about one to two days in advance.

Preparation

  • Please turn off all sprinklers the day before and the day of application. Dry pavement allows the product to perform better.
  • Do not park on the street the day the work is scheduled.
  • Do not drive on the wet material until after the sand has been applied. It will splatter onto your vehicle and track onto your driveway. Residue on your vehicle should be immediately washed off with soap and water or use a degreaser at a car wash. The material can be washed off your drive or will wear off in 2-6 weeks.
  • Sealant can be difficult to remove from tires and shoes. Please avoid treated areas until the sand has been applied.
  • Keep children and pets away from the street until the sand has been removed.
  • Reschedule any contractors, landscapers or deliveries on days work is scheduled.

Project Contacts

  • James Puls, Construction Project Manager

    City of Lincoln, LTU Project Delivery
    Phone: 402-525-5641
    Email: jpuls@lincoln.ne.gov

  • Marc Rosso, Construction Engineer

    City of Lincoln, LTU Project Delivery
    Phone: 531-207-3244
    Email: mrosso@lincoln.ne.gov