“A” Street from Smoky Hill Road to 98th Street Water Main Extension

Updated September 17, 2019

Construction is underway on a water main extension project in the area of “A” Street from Smoky Hill Road (approximately 87th Street) to 94th Street. Work will include extending the existing water main to the east in order to better serve new development and a growing customer base.

Storm and sanitary sewer infrastructure that serves the development area will be installed at the same time.

Access During Construction

“A” Street from 84th to 98th streets reopened to through traffic on September 17, 2019. Temporary lane closures may be necessary to finish the remaining improvements included in the project. Motorists are urged to use caution around construction crews.

  • Project Area A Street reopened Tue., Sep. 17, 2019

Re-center mapFull-screen

Schedule

The project began July 24, 2019 and is expected to be completed in October 2019.

Project Contacts

  • Russ Gasper, Construction Engineer

    Water Main Extension Project
    City of Lincoln, LTU Project Delivery
    Phone: 402-580-8438
    Email: rgasper@lincoln.ne.gov

  • Daran Brown

    Sanitary Sewer Project
    City of Lincoln, Wastewater System
    Phone: 402-318-9715
    Email: dbrown@lincoln.ne.gov

  • TJ Osborn

    TJ Osborn Construction, Inc.
    Phone: 402-464-4235