Water Main Replacement Project Sunburst from Sumner to “A” • Cotner from Franklin to 48th

Updated August 8, 2019

Construction began in August 2019 on a water main replacement project in the area of Cotner Boulevard and “A” Street. Work will include replacing existing water mains at 45th Street between Franklin and Sumner streets, Sunburst Lane between Sumner and “A” streets, Ridgeway Road between Sunburst Lane and Brian Circle, and Cotner from Franklin to the east side of 48th.

Access During Construction

48th Street
Two-way traffic will be maintained on 48th Street.
Cotner Boulevard
Cotner Boulevard will be closed to through traffic from South Street to 48th Street and to southbound traffic from “A” Street to 48th Street. Sumner Street will also be closed at Cotner Boulevard during this construction phase.
45th Street / Sunburst Lane
45th Street / Sunburst Lane shall be closed to through traffic between Franklin Street and “A” Street.
“A” Street
Two-way traffic will be maintained on “A” Street, and concrete barriers will be in place to protect the work area.
Ridgeway Road
Ridgeway Road shall be closed to through traffic between Sunburst Lane and Bryan Circle.

Access to adjacent businesses and residences will be maintained but may be restricted at times during construction operations. All access restrictions will be coordinated with the Contractor, City and property owners.

Project Area

  • Project Area

Re-center mapFull-screen

Project Contacts

  • Mark Miller, Construction Project Manager

    City of Lincoln, LTU Project Delivery
    Phone: 402-416-5348
    Email: mmiller@lincoln.ne.gov

  • Tom Cline, Project Manager

    K2 Construction
    Phone: 930-229-7706