Antelope Park and Rock Island Trail Project South Street to Calvert Street

Updated July 12, 2019

Scope of Work

This project includes repairs of the stair structure and bikeway, and installation of storm sewer along the Rock Island Trail from South Street to Calvert Street. Project benefits include eliminating standing water in low areas, reducing mud and ice on the trail for improved trail safety, and improved pedestrian school routes.

2019 construction will take place between Sheridan Boulevard and Calvert Street. Work includes bikeway repair, storm sewer installation and landscaping along the bikeway.

Access During Construction

Sheridan Boulevard will have closures below the Penny Bridges July 16 and 17, 2019, from 9 a.m. to 2 p.m. each day. Westbound lanes will be closed Tuesday, July 16, as well as the sidewalk on the north side of the street. Eastbound lanes will be closed Wednesday, July 17, as well as the sidewalk on the south side of the street. Digital signs will alert traffic to upcoming work and lane closures.

During construction, work areas along the bikeway shall be closed with detours marked for pedestrians and cyclists. The recommended trail detour is Van Dorn, 31st and and Calvert Streets.

    • Trail closure
    • Detour Detour

Re-center mapFull-screen

Schedule

Construction began September 24, 2018. Wet weather in the fall caused delays and construction was suspended for the winter. Work is expected to resume July 8, 2019, and the project is anticipated to be completed by September 8, 2019.

Project Contacts

  • Mark Miller, Project Manager

    City of Lincoln, LTU Project Delivery
    Phone: 402-416-5348
    Email: mmiller@lincoln.ne.gov

  • Derek Bookstrom, Project Manager

    Bookstrom Construction
    Phone: 402-432-0436
    Email: derek@hrbookstrom.com

  • Tim Zach, Project Engineer

    City of Lincoln, Watershed Management
    Phone: 402-441-7018
    Email: tzach@lincoln.ne.gov