2019 Citywide Arterial Street Rehabilitation Project

Updated July 3, 2019

Scope of Work

The 2019 citywide pavement rehabilitation project includes work on three major streets in the city. At each location, street improvements will include mill and overlay of the existing asphalt, pavement repairs, joint sealing and new pavement markings. Pedestrian ramps may be reconstructed to meet federal and local standards, as necessary.

Locations

  • S Folsom from W Pioneers to W South
  • NW 48th from W Fletcher to W Craw
  • W Van Dorn from S Coddington to Railroad Tracks

Schedule

Construction on NW 48th Street from W Craw Street to W Fletcher Avenue is scheduled to begin July 8, 2019, and the street will be closed through early August. Work at the other locations will occur in 2019, based on the selected contractor’s schedule.

Access During Construction

The streets will be closed to through traffic during mill and overlay (resurfacing) operations. Message signs will be used for advance notification of street closures. The city will work closely with the neighborhoods to allow local traffic to pass into and through the area. Construction flagging operations will need to occur at times.

NW 48th Street  (Starting July 8, 2019)

NW 48th Street will be closed to through traffic from W Craw Street to W Fletcher Avenue. Motorists will detour using W Mathis Street, NW 38th Street, Airport Road, NW 31st Street and Highway 34 (see map). W Mathis Street will remain accessible to detouring traffic via flagging operations while work is occuring on NW 48th Street between W Craw and W Mathis streets.

  • Construction Begins July 8   
  • Detour class   
  • Project Location   

Re-center mapFull-screen

Project Contacts

  • Gaylon Masek, Construction Project Manager

    City of Lincoln, LTU Project Delivery
    Phone: 402-416-7486
    Email: gmasek@lincoln.ne.gov

  • Marc Rosso, Construction Engineer

    City of Lincoln, LTU Project Delivery
    Phone: 531-207-3244
    Email: mrosso@lincoln.ne.gov