Rokeby from 70th to 84th Paving and Safety Improvement Project

Updated October 14, 2019

Scope of Work

This project includes grading and construction of new pavement on Rokeby Road from 70th Street to Carpathian Lane. Turn lanes were added at the 70th Street and Rokeby Road intersection, and roundabouts were built at the intersections of Rokeby Road with 73rd Street and Carpathian Lane. The project also includes storm sewer system improvements to enhance drainage, ADA-accessible sidewalks and LED street lights. The new street is designed to accommodate the potential for widening to four lanes in the future to support traffic and residential growth.

Access During Construction

Work was performed under a full street closure on Rokeby Road from 70th to 84th streets.

  • Project Area

Re-center mapFull-screen

Schedule

Construction began September 24, 2018, and Rokeby Road re-opened to traffic in mid-October 2019.

Project Contacts

  • Mark Miller, Project Manager

    City of Lincoln, LTU Project Delivery
    Phone: 402-416-5348
    Email: mmiller@lincoln.ne.gov

  • Marc Rosso, Construction Engineer

    City of Lincoln, LTU Project Delivery
    Phone: 531-207-3244
    Email: mrosso@lincoln.ne.gov

  • Mitch Climer, Project Contractor

    Hawkins Construction
    Phone: 402-616-6538
    Email: mclimer@hawkins1.com