Apply for a Right Of Way Construction Permit
Accela Citizen Access
- permits.lincoln.ne.gov/CitizenAccess
- apply for permits and check the status of applications
All contractors must register for an account in Accela Citizen Access. Please select "Contractor" as the account type.
ROW and FOP Contractor Requirements
ROW Contractor Requirements
- Complete the ROW Contractor Form
and submit to Building and Safety (address on form)
- Pay $250 account setup fee
- Submit bond and insurance (see ROW Construction Permit Insurance & Bond Requirements
)
- Maintain good standing with the City of Lincoln in all business and legal matters
FOP Contractor Requirements
- Complete the FOP Contractor Form
- Pay $250 account setup fee
- Provide five years’ experience for working in joint tenancy communication systems
- ATT / SBC / other RBOC-approved contractor
- Project list showing this experience
- Provide list of business-owned equipment
- Owned equipment list for work type requested (IE splicing trailers, cable reel trailers, excavators, bore rigs, etc…)
- Submit all of the above to Building and Safety (address on form)
- Carry insurance with additional insured for the following:
- City of Lincoln
- Unite Private Networks
- NebraskaLink
- Level 3
- CenturyLink
- University of Nebraska
- Allo Communications
- Windstream
- Submit bond and insurance (see FOP Construction Permit Insurance & Bond Requirements
)
- Maintain good standing with the City of Lincoln in all business and legal matters