Transit Capital Assistance


Transit Capital Assistance

Handivan Replacement

Project Description:
Replace 10 Handivans with hybrid electric vehicles using $640,000 of Recovery Act funding and $510,000 of previous year's federal grant.
Estimated Cost:
$1,150,000
ARRA Funds:
$640,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Bus Replacement

Project Description:
Replace 14 BioDiesel 30 ft. Buses and 3 small light-duty hybrid vans using $1,698,100 of Recovery Act funding and $3,470,000 of previous year's federal grant.
Estimated Cost:
$5,168,100
ARRA Funds:
$1,698,100
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Bike Racks

Project Description:
Purchase and install 77 Bike Racks for entire fleet of buses.
Estimated Cost:
$155,000
Estimated Cost:
$155,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Shelter Rehab

Project Description:
Rehabilitate bus shelters in the Downtown area.
Estimated Cost:
$449,000
ARRA Funds:
$449,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Elevator Replacement

Project Description:
Replace the ADA elevator in the StarTran Administration Building.
Estimated Cost:
$125,000
ARRA Funds:
$125,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Bus Wash Replacement

Project Description:
Replace the bus wash equipment.
Estimated Cost:
$200,000
ARRA Funds:
$200,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

AVL Enhancements

Project Description:
Install Trip Planner and message boards to enhance the AVL system.
Estimated Cost:
$150,000
ARRA Funds:
$150,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Hybrid Tools/Equipment

Project Description:
Purchase tools and equipment necessary to maintain hybrid vehicles.
Estimated Cost:
$10,958
ARRA Funds:
$10,958
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

ADA Funding

Project Description:
Reimburse ADA Paratransit services, up to 10% of ARRA stimulus funding
Estimated Cost:
$370,000
ARRA Funds:
$370,000
Project Sponsor:
City of Lincoln Public Works Department - StarTran
Project Contact:
Larry Worth - 441-8600

Recovery Links

Recovery.gov Recovery.nebraska.gov Read the full text of the American Recovery and Reinvestment Act (PDF Format)

Contact Information

Chad Blahak, P.E., MBA
Stimulus Projects Coordinator
Public Works & Utilities Department
555 South 10th Street, Suite 203
Lincoln, Nebraska 68508

Phone: (402) 441-7548
cblahak@lincoln.ne.gov

The public information contained herein is furnished as a public service by the City of Lincoln. Although the information is believed to be accurate and reliable, the City of Lincoln assumes no responsibility for any error appearing in the information furnished and makes no warranties, either expressed or implied, concerning the accuracy, completeness, reliability, or suitability of the information for any particular use. Furthermore, the City of Lincoln assumes no responsibility for the use of the information provided and if precise information is needed, it is highly recommended that you verify the information by consulting the official sources of the information. In some cases, the information may need to be updated.

Validate

ARRA Projects