Lincoln on the Move invested in improvements to several streets in the College View Neighborhood. These improvements included a mill and overlay of the existing surface and base repairs where required. The following streets were included:
Additional work with other funding sources included upgrades to the existing curb ramps to comply with the Federal Americans with Disabilities Act (ADA) requirements and priority sidewalk repairs.
This project was programmed as a part of the commitment to voters to invest significant sales tax funds into improvement of existing streets. The project was funded jointly from the Street Improvement Vehicle Tax – Residential Rehab fund (aka-Wheel Tax) and ¼ cent sales tax for street in accordance with ballot language.
Construction took place in 2022 and 2023.
James Puls, Construction Project Manager City of Lincoln Transportation and Utilities jpuls@lincoln.ne.gov 402-525-5641
Marc Rosso, Construction Engineer City of Lincoln Transportation and Utilities mrosso@lincoln.ne.gov 531-207-3244