This project will improve Randolph Street from 40th to 56th streets through a mill and overlay of the existing surface and selected base repairs where required. Additional work will include pavement markings, upgrades to the existing curb ramps to comply with the Federal Americans with Disabilities Act (ADA) requirements.

Project Location

Funding Details

This project is programmed as a part of the commitment to voters to invest significant sales tax funds into improvement of existing streets. The project will be funded jointly from the Highway Allocation Funds (aka-Gas Tax) and ¼ cent sales tax for streets in accordance with ballot language. Until more detailed information is known, the total project estimate and funding split is an assumption.

Schedule

This project is expected to begin construction in August 2022 and be completed in the fall.

Access During Construction

Randolph Street will be closed to through traffic during construction. Access to individual properties will be maintained as the construction process allows. The traveling public is encouraged to find alternative routes and to use the WAZE app for assistance.

Project Contacts

  • Construction Project Manager

    Mark Miller
    City of Lincoln, LTU Project Delivery
    mmiller@lincoln.ne.gov
    402-416-5348

  • Construction Administration

    Marc Rosso
    City of Lincoln, LTU Project Delivery
    mrosso@lincoln.ne.gov
    531-207-3244

  • Project Contractor

    Jordan Damkroger
    MTZ Construction
    402-440-9230