This project paved South 70th Street at Carger Lane to help serve growth in the community by improving the safety and capacity of the transportation system. The project included construction of a new roundabout at 70th Street and Carger Lane, new sidewalk with curb ramps to comply with the Americans with Disabilities Act (ADA) requirements, water main construction and other utility work.
Construction was completed in 2023.
Marc Rosso City of Lincoln, LTU Project Delivery mrosso@lincoln.ne.gov 531-207-3244
Brian Jueneman Olsson bjueneman@olsson.com 402-304-6571