This project repaired issues with the W Adams Street bridge located over North Park Road and the Union Pacific Railroad tracks west of the NW 12th Street intersection. Repairs included installing new expansion joints at the ends of the bridge, repairing the median on the bridge, repairing deterioration with the concrete columns under the bridge, and installing new bridge drains underneath the structure.
Construction took place in 2024.
James Puls, Construction Project Manager City of Lincoln, LTU Project Delivery jpuls@lincoln.ne.gov 402-525-5641
Greg Hutmacher, Design Engineer Speece Lewis Engineers ghutmacher@speecelewis.com 402-770-7119