This project will reconstruct water mains along Prescott Avenue from 52nd to 54th streets and 52nd Street from Pioneers Boulevard to Prescott Avenue. This work is being coordinated with a street resurfacing project, which will take place after the water main replacement is complete.
Water main construction is expected to take place from November 2021 through spring of 2022. Pavement resurfacing will take place after the water main work is completed. Project dates are subject to change due to weather and unforeseen circumstances.
Streets will be closed to through traffic in the work area during construction. Access to individual properties will be maintained.
City of Lincoln, LTU Project Delivery Email: jsundeen@lincoln.ne.gov Phone: 402-416-5341
Bookstrom Construction Phone: 402-432-0098
Union College Neighborhood Street Improvement Project