40th from “A” to “O” - Water Main Project

Project Summary

The project will install a new 16-inch water main, replacing the existing 6-inch and 16-inch water mains along 40th Street from “A” to “O” streets.

This work is being coordinated with a street improvement project, which will take place after water main replacement is completed.

Project Location

Funding

Schedule

Construction could begin as early as spring 2025 and is anticipated to be completed in fall 2025.

Access During Construction

The northbound lane of 40th Street will be closed to traffic during construction. A southbound lane will be maintained but some restrictions may be necessary. Short-term temporary intersection closures will be needed as the project progresses. Related: Construction Phasing Details(, 0B)

Public Open House

Tuesday, April 1, 2025 5:00 – 7:00 p.m. Randolph Elementary School, 1024 South 37th Street

Meeting Materials  Project Fact Sheets(, 0B) Meeting Displays(, 0B) Project Design Maps(, 0B)

Project Contacts

  • James Puls, Construction Project Manager
    City of Lincoln, LTU Project Delivery
    jpuls@lincoln.ne.gov
    402-525-5641

  • Russ Gasper, Construction Engineer
    City of Lincoln, LTU Project Delivery
    rgasper@lincoln.ne.gov
    402-580-8438