The purpose of this project is to preserve and extend the service life of existing facilities and enhance safety by using safety conscious design. The improvements will satisfy existing and future traffic needs and conditions in a manner conducive to safety, durability, and economy of maintenance. The need of the project is to address substandard curb and pavement conditions; narrow pavement; substandard curb ramps; substandard inlet tops; and appropriate pedestrian crossing devices.
This project will improve Adams Street between 38th and 49th streets. The project includes concrete replacement and repairs, grading, milling, and resurfacing of the street. It will reconstruct pedestrian ramps, curbs and gutters, and replace the pedestrian crossing signal near North 46th Street to increase safety for vehicles and pedestrians.
This work is being coordinated with a water main replacement project on Adams Street from 36th to 41st streets. More info: Water Main Replacement Project
Acquisition of right-of-way is not anticipated for this project, however construction easements will be needed to facilitate work on this project.
Construction is anticipated to take place in 2025 and 2026.
James Puls, Construction Project Manager City of Lincoln, LTU Project Delivery jpuls@lincoln.ne.gov 402-525-5641
Russ Gasper, Construction Engineer City of Lincoln, LTU Project Delivery rgasper@lincoln.ne.gov 402-580-8438