No trees have been identified for removal on this project. The Contractor shall protect all trees that are not required to be removed in this project. Where necessary, the Contractor may have to hand dig around tree to prevent damage to roots.
Any form of protection chosen by the Contractor, such as fences, ropes, etc., shall be furnished, erected, and maintained by the Contractor. Any trees that appear to have significant root damage caused by excavation or any tree that needs trimmed in or from the public right-of-way, shall be coordinated with the Project Manager or his representative who shall contact the City Arborist to verify any necessary actions in saving, trimming, or removing the damaged tree.
Tree protection completed in conformance with these Special Provisions and accepted by the City’s Project Manager, shall not be measured and paid for separately. Such cost shall be considered a part of the unit prices for which direct payment is made.