Final Edition FY 2020/21 - 2025/26

The approved Final Edition of the 2020/21 - 2025/26 Capital Improvement Program (CIP) is now available. This CIP was found to be in conformance with the Lincoln/Lancaster County 2040 Comprehensive Plan - 2016 Update. The first two years of the CIP become the Capital Budget for fiscal years 2020/21 and 2021/22 which will begin on September 1 of 2020 and 2021. 

Download entire CIP(PDF, 11MB) document.

Amendments

CPC20013 - Project P:Local Generation Rokeby Environmental, Regulatory & Safety. The amendment is to include the remodel of the Rokeby Generating Station Operations Center. LES staff determined that the remodel of the Operations Center is necessary to accommodate increased staffing. The amendment updated the 2020/21 budget.